From the
organisers of
Concrete Show Logo
 

Huge beams lifted into place for new HS2 bridge near Kenilworth

A concrete bridge deck under construction The pre-cast concrete bridge beams were manufactured in Ashfordby, Melton Mowbray, by a specialist civil and structural engineering partnership FTB JV – a joint venture formed of Freyssinet, Tierra Armada and Roger Bullivant.

A 91m-long bridge designed to carry HS2 over the existing West Coast Main Line near Kenilworth is taking shape, following the successful installation of 83 giant pre-tensioned concrete beams.

Installed using a 500-tonne capacity Demag CC2500 crawler crane, the horizontal beams collectively form the deck of the bridge structure that will eventually be used as part of the high-speed rail line.

Each beam measures 19 metres in length, with 81 beams weighing 18.1 tonnes and two beams weighing 33 tonnes – a total of 1,532.1 tonnes. The Carol Green rail bridge structure will, on completion, span over 20 metres, 7.5 metres in height and 91 metres in width.

Before the high-speed tracks are laid, the bridge will form part of a haul road for HS2 construction vehicles. It will connect the north and south side of the West Coast Main Line, providing a temporary route from the Aston Martin roundabout to Burton Green. This will reduce construction traffic through the Balsall Common road network and minimise disruption for local communities.

Once operational, the bridge structure and its embankments will take the new HS2 railway diagonally over the existing West Coast Main Line.

 

An aerial view of HS2's Carol Green Underbridge under construction

The successful operation was delivered by a team of 30 people over 13 consecutive weekends by HS2’s construction partner Balfour Beatty VINCI (BBV). The pre-cast concrete bridge beams were manufactured in Ashfordby, Melton Mowbray, by a specialist civil and structural engineering partnership FTB JV – a joint venture formed of Freyssinet, Tierra Armada and Roger Bullivant. 

The final phase of construction sees the installation of parapet walls and acoustic barriers, as well as backfilling and landscaping – with full completion expected in Autumn 2025.

Jack King, HS2 project manager, said: “It takes an immense amount of skill and precision to carry out such a challenging feat of engineering and to construct these colossal structures. 

“We’re proud to have reached this stage of the bridge’s completion ahead of schedule, which is testament to the entire team. Thank you to everyone involved onsite as we continue to pave the way for Britain’s new high-speed line.”

Route-wide, HS2 is building more than 500 bridging structures – including over 50 major viaducts which will stretch for a combined total of 15 km across valleys, rivers, roads and flood plains.